Animation Producer Dialog, Schedule Section
Contains controls that let you create and modify tasks for a schedule simulation. Displays when
is chosen in the Animation Producer dialog.Components of the Schedule graph are as follows:
- The graph displays each task from its start to its end times.
- Parent tasks display in black.
- Each row on the time line correlates to a row in the tree view.
- Header rows for the tree display with a cyan background in the schedule.
You can edit the graph by clicking and dragging the task entries along the timeline.
Setting | Description |
---|---|
Animation Tree View | Displays a list of the project and tasks associated with a schedule. |
Schedule Panel List Box | This expandable/collapsible section displays tasks filtered by the Animation list box selection and the filter row. The show/hide icon to the left of the Schedule Panel title expands/collapses the list box. Columns in the list box may be resized and displayed or hidden as required. To display/hide a column, right-click in the column heading row and check/uncheck the required column. To view all available property columns, choose List at the bottom of the right-click menu. The Show/Hide Tools dialog opens. Turn on any property columns you want to display in the Schedule Panel. The top row in the list box is a filter row. You can filter tasks by name, unique ID, start/end times of tasks, etc. You can clear the filter row by typing the key-in ANIMATOR SCHEDULE CLEARFILTER. You can select multiple tasks and change a common property on all these tasks simultaneously. Properties that can be changed in this manner are Start Color, Finish Color, Start Transparency, Finish Transparency and [Activity] Type. The most common task property columns displayed are as follows. You can change the property value unless otherwise noted.
|
Right-Click Menu | When you right-click a task in the Schedule Panel, a context-sensitive menu displays the available options for the selected task. These can include the following:
|
File > Schedule > Import | Opens the Import Schedule dialog, which is used to import a schedule file. |
File > Schedule > Update | Updates the tasks in the schedule to match any changes made in the external schedule created in, for example, Microsoft Project or Primavera. |
File > Schedule > Export | Opens the Export Schedule dialog, which is used to export a schedule file. |
File > Schedule > Delete | Deletes a schedule. |
File > Schedule > Compare Schedules | Opens the Compare Animations tool, which allows you to compare two identical schedules by the type of start and finish times selected in the Schedule Simulation section of the Animation Settings dialog (Animation Producer dialog's ).
|